59 MW
of combined generating capacity
Wind energy powering the territory
We are currently constructing two windfarms in the municipality of Karstula.
Our intention is to have both wind farms in operation by the end of 2023 and to remain as a long term owner and operator of the two windfarms, and a member of the local community in Karstula.
All together 168,000 MWh of electricity produced annually on average
Equals the yearly consumption of
20,000 Finnish households
137,760 tons of CO2
avoided annually
(if produced with coal)
Koiramäki
The wind farm Koiramäki will consist of 5 Nordex N163 wind turbines with an installed capacity of 5.9 MW each.
The tip height of the turbines will be 230 metres.
Construction of the wind farm will start in Summer 2022 and the commissioning of the wind farm is planned for Autumn 2023.
The wind farm Koiramäki is located in the forest around the Koiralampi Pond some 4 km:s south of the village Vastinki in the municipality of Karstula.

Mustalamminmäki
The wind farm Mustalamminmäki will consist of 5 Nordex N163 wind turbines with an installed capacity of 5.9 MW each.
The tip height of the turbines will be 230 metres.
Construction of the wind farm will start in Summer 2022 and the commissioning of the wind farm is planned for Autumn 2023.
The wind farm Mustalamminmäki locate in the forest around the peat extraction site at Suurisuo some 2 km:s west of highway 13.

The milestone of the projects
In order to demonstrate, among all stakeholders, our reputations as a serious, reliable and professional partner we make every single step of the project clear and transparent.

- 31/12/2023
Commissioning of windfarm
Commissioning of windfarm
December 31, 2023Commissioning of windfarm
- 01/07/2023
Erection of WTGs
Erection of WTGs
July 1, 2023Erection of WTGs
- 01/06/2023
Transports of WTG components to site
Transports of WTG components to site
June 1, 2023Transports of WTG components to site
- 01/11/2022
Foundation works
Foundation works
November 1, 2022Foundation works
- 01/06/2022
Construction start at site
Construction start at site
June 1, 2022Construction start at site
Impact assessments
Mustalamminmäki – Wind farm plan impact study – Finnish
Mustalamminmäki – Appendix 4 – noise and flicker study
Mustalamminmäki – Appendix 5 – visual impact analysis
Mustalamminmäki – Appendix 6 – landscape analysis
Mustalamminmäki – Appendix 7 – combined landscape analysis
Mustalamminmäki – Appendix 8 – nature study
Mustalamminmäki – Appendix 9 – Archeological Inventory
Mustalamminmäki – Appendix 10 – study on broadcasting signals
Koiramäki – wind farm plan impact study
Koiramäki – Appendix 4 – noise and flicker study
Koiramäki – Appendix 5 – visual impact analysis
Koiramäki – Appendix 6 – landscape analysis
Koiramäki – Appendix 7 – combined landscape impact analysis
Koiramäki – Appendix 8 – archeological inventory
Koiramäki – Appendix 9 – nature study
Koiramäki – Appendix 10 – capercaillie and black gouse courtship study